How to connect electricity to a house or land: nuances of connection design price

Every landowner at some point begins to think about supplying him with electricity. This work can be done not only during the construction of a country house, but also after putting the house into operation.

Even before you start connecting the network, power should be determined, necessary for a full supply of electricity to a country house, calculate the distance, on which electrical networks must run in relation to the house, as well as learn, whether there is the required network capacity in this area.

List of required documents

If you are determined to bring to the land an electrician, then first of all you need to make an application of the established sample and apply to the organization, which includes maintenance of electrical networks at the location of the site.

There you must issue a permit to connect electricity. In addition to the statement, you will have to prepare and copy the documents, with the signatures of a notary:

  1. Passport and identification code.
  2. Documents, establishing ownership of the site and the house.
  3. Documents for land and house.
  4. In that case, if the summary is requested by a representative, then a power of attorney is required.
  5. Electrification project of the house and the plot, which must contain information about all energy consuming devices and their power consumption.
  6. Building permit. Needed to supply electricity to the site, where there are no buildings.

After preparing the above documents, they must be sent by registered mail. It will be useful to add to them a description of the attached documents.

In that case, if a document does not appear in the package you sent, then the organization is obliged to inform you of this fact no later than 6 days from the date of receipt of documents.

In some cases, you may be asked to send originals of certain documents from the list above., to confirm this information. The documents sent by you will be used by the organization as a basis for drawing up technical conditions, without which it is impossible to supply electricity to the site.

They should reflect the technical characteristics of the introduction of electricity in a private home: This means that a single-phase or three-phase cable will be used to supply electricity to the house.

When you meet all the conditions of this order, you will already have every right to start supplying electricity. An important point is that, that the technical conditions must be met no later than two years from the date of their compilation.

Sometimes this can happen, that due to the peculiarities of the technical conditions of electrical networks it is impossible to supply electricity to the site. A situation is also possible, when the rated load capacity exceeds the rated value of the network.

In such cases, the organization must notify the customer of this fact in writing. It is not possible to appeal the decision.