Pressure heating system: rules and regulations snip, act of pressing the heating system

To put the heating into operation, be sure to flush and pressurize the system. After completing this procedure, the act is completed, which confirms, that the installation of the heating network is done correctly. Employees authorized to perform this work are required to comply with all applicable regulations.

SNiP pressing rules

Standards for crimping the heating system are described in the following documents, like Snip 41-01-2003, and another 3.05.01–85.

Conditioning, ventilation and heating - SNiP 41-01-2003

It is possible to carry out hydraulic checks of water heating systems only at a positive temperature in the premises of the house. Besides, they are must withstand water pressure at least 0,6 MPa without damage to tightness and destruction.

During the test, the pressure must not be higher than the limit value for the heating devices installed in the system., pipelines and fittings.

Internal sanitary systems - 3.05.01-85

According to this SNiP rule it is necessary to carry out check of water systems of heat supply and heating at switched off expansion vessels and boilers by hydrostatic pressure, equal 1,5 working, but no less 0,2 MPa at the bottom of the system.

It is considered, that the heating network has been tested, if it lasts 5 minutes under test pressure and will not fall more than 0,02 MPa. in addition, there should be no leaks in the heating equipment, welds, fittings, threaded connections and pipes.

Conditions for crimping

The test work is performed correctly, if all the necessary requirements are met. Example, third-party work may not be performed on the test object, and the test must be led by the shift supervisor.

Crimping is carried out only according to the program, approved by the company's chief engineer. It determines: the order of actions of employees and the technological sequence of the inspection. Safety measures of performed and current works are also taught, produced at adjacent facilities.

Strangers while pressing the heating system, test devices must not be switched on or off, only employees remain in place, participating in the inspection.

When carrying out work on adjacent sites, it is essential to provide reliable fencing and disconnection of test equipment.

Inspection of heaters and pipes is allowed only at operating pressure values. When the heating system will be crimped, acts fill, to confirm tightness.

Crimping procedure

This method of testing the heating system involves the implementation of hydraulic tests:

  • Heat exchangers;
  • Boilers;
  • Pipes.

Thus it is possible to detect leaks, which indicate the depressurization of the network.

Before testing the heating system with plugs, the heat supply system should be isolated from the water supply, visually assess the reliability of all connections, and also to check up serviceability and a condition of shut-off valves.

After that the expansion tank and a copper for washing of radiators are switched off, pipelines from various deposits, garbage and dust.